Overhead cranes—often called bridge cranes—are the quiet workhorses that keep heavy industry moving. This long-form walkthrough takes you behind the scenes of a mega-project crane install. We’ll cover final load testing and handover—with the same checklists pro installers use.
Bridge Crane Basics
At heart, a bridge crane is a bridge beam that spans between two runway beams, carrying a trolley-mounted hoist for precise, vertical picks. The result is smooth X-Y-Z motion: long-travel along the runway.
You’ll find them in fabrication bays, steel plants, power stations, oil & gas shops, precast yards, and logistics hubs.
Why they matter:
Safe handling of very heavy, unwieldy loads.
Huge efficiency gains.
Repeatable, precise positioning that reduces damage.
Support for pipelines, structural steel, and big machinery installs.
What This Install Includes
Runways & rails: runway girders with crane rail and clips.
End trucks: wheel assemblies that ride the rail.
Bridge girder(s): cambered and pre-wired.
Trolley & hoist: cross-travel carriage with lifting unit.
Electrics & controls: power supply, festoon or conductor bars.
Stops, bumpers & safety: overload protection, e-stops.
Depending on capacity and span, the crane might be a single-girder find a contractor 10-ton unit or a massive double-girder 100-ton system. The choreography is similar, with heavier rigs demanding extra controls and sign-offs.
Pre-Install Prep
A clean install is mostly planning. Key steps:
Drawings & submittals: Approve general arrangement (GA), electrical schematics, and loads to the structure.
Permits/JSAs: Permit-to-work, hot work, working at height, rigging plans.
Runway verification: Survey columns and runway beams for straightness, elevation, and span.
Power readiness: Confirm conductor bars or festoon supports, cable trays, and isolation points.
Staging & laydown: Lay out slings, shackles, spreader bars, and chokers per rigging plan.
People & roles: Appoint a lift director, rigger, signaler, and electrical lead.
Millimeters at the runway become centimeters at full span. Measure twice, lift once.
Getting the Path Right
If rails are off, nothing else will run true. Targets and checks:
Straightness & elevation: Laser or total station to set rail height.
Gauge (span) & squareness: Check centerlines at intervals; confirm end squareness and expansion joints.
End stops & buffers: Verify clearances for bumpers at both ends.
Conductor system: Mount conductor bars or festoon track parallel to the rail.
Log final numbers on the ITP sheet. Correct now or pay later in wheel wear and motor overloads.
Putting the Span in the Air
Rigging plan: Choose spreader bars to keep slings clear of electricals. Taglines for swing control.
Sequence:
Lift end trucks to runway level and set temporarily on blocks.
Rig the bridge girder(s) and make the main lift.
Land the bridge on the end trucks and pin/bolt per GA.
Verify camber and bridge square.
Prior to trolley install, bump-test long-travel motors with temporary power (under permit): ensure correct rotation and brake release. Re-apply LOTO once checks pass.
Hoist & Trolley
Trolley installation: Mount wheels, align wheel flanges, set side-clearances.
Hoist reeving: Lubricate wire rope; verify dead-end terminations.
Limits & load devices: Check overload/SLI and emergency stop.
Cross-travel adjustment: Verify end stops and bumpers.
Pendant/remote: Install pendant festoon or pair radio receiver; function-test deadman and two-step speed controls.
Grinding noises mean something’s off—stop and inspect. Fix the mechanics first.
Drive Tuning & Interlocks
Power supply: Conductor bars with collectors or a festoon system.
Drive setup: Enable S-curve profiles for precise positioning.
Interlocks & safety: Zone limits near doors or mezzanines.
Cable management: Keep loops short, add drip loops where needed.
Commissioning crews love clean labeling and clear folders. If it isn’t documented, it didn’t happen—put it in the databook.
Trust but Verify
Inspection Test Plan (ITP): Hold/witness points for rail alignment, torque, electrical polarity, limit settings.
Torque logs: Re-check after 24 hours if required.
Level & gauge reports: Attach survey prints.
Motor rotation & phasing: Confirm brake lift timing.
Functional tests: Jog commands, inching speeds, limits, overloads, pendant/remote range.
A tidy databook speeds client acceptance.
Proving the System
Static load test: Apply test weights at the hook (usually 100–125% of rated capacity per spec).
Dynamic load test: Travel long-run, cross-travel, and hoist at rated speed with test load.
Operational checks: Emergency stop shuts down all motions.
Training & handover: Maintenance intervals for rope, brakes, and gearboxes.
When the logbook is clean, the crane is officially in service.
Applications & Use Cases
Construction & steel erection: placing beams, trusses, and precast.
Oil & gas & power: generator and turbine assembly.
Steel mills & foundries: large part transfer.
Warehousing & logistics: high throughput lanes.
Once teams learn the motions, cycle times drop and safety improves.
Controls that Matter
Rigging discipline: dedicated signaler and stop-work authority.
Lockout/Tagout: clear isolation points for electrical work.
Fall protection & edges: approved anchor points, guardrails on platforms, toe boards.
Runway integrity: regular runway inspection plan.
Duty class selection: overspec when uncertainty exists.
Safety isn’t a stage—it's the whole show.
Troubleshooting & Pro Tips
Crab angle/drift: re-check runway gauge and wheel alignment.
Hot gearboxes: misalignment or over-tight brakes.
Rope drum spooling: check fleet angle and sheave alignment.
Pendant lag or dropout: shield noisy VFD cables.
Wheel wear & rail pitting: add rail sweeps and check clip torque.
Little noises are messages—listen early.
Quick Answers
Overhead vs. gantry? Choose per site constraints.
Single vs. double girder? Singles are lighter and cheaper; doubles carry heavier loads and give more hook height.
How long does install take? Scope, bay readiness, and tonnage rule the schedule.
What’s the duty class? FEM/ISO or CMAA classes define cycles and service—don’t guess; size it right.
Why Watch/Read This
If you’re a civil or mechanical engineer, construction manager, shop supervisor, or just a mega-project fan, this deep dive makes the whole process tangible. You’ll see how small alignment wins become big reliability wins.
Looking for a clean handover databook index you can reuse on every project?
Download your pro bundle so your next crane goes in cleaner, faster, and right the first time. Save it to your site tablet for quick reference.
...